Project Details

34 Queens Road, Taringa 4068

Number Proposed Dwellings

9 Units

Estimated Project Time Frame

12 months

Project Updates

Project Update as at 27th September 2017:

  • House Will Be Removed To Temporary New Position
  • Top 2 Units Under Construction
  • Units 3 & 4 Stripping from Formwork from Slab in progress
  • 6 Sales + 2 EOI's
  • New video update loaded above

Project Update as at 28th August 2017:

  • Units 1 - 4 blockwork now completed
  • Basement carpark complete
  • Blockwork for Units 5 and 6 under construction
  • All plumbing and services connected to Units 1-5
  • Uprights for supporting slab erected and ready for concrete pour
  • House to be relocated and renovated on completion of rear 8 Units
  • New photos and site video uploaded
  • Expected Completion Date: December 2017

Project Update as at 22nd July 2017:

  • Marketing material complete and ready for issuing
  • OP works approvals received and onsite works complete
  • Stage 1 building approval issued for lower level units
  • Stage 2 building approval awaiting QFES signoff
  • Footings to lower level have been poured
  • Lower level ground slab poured
  • Block work and formwork in progress
  • New site photos uploaded to image gallery

Project Update as at 14th June 2017:

  • Footings and concrete slab poured
  • BA stage 1 been approved
  • Plumbing approved
  • All mains, sewerage and water electricity connected
  • 8 presales – will be finalised when disclosure documents issued

Project Update as at 28th April 2017:

Project update from Vested Capital

Updated photos loaded to website

Project Update as at 15th March 2017:

Project update from the development company Vested Capital

Project Update as at 22nd December 2016

  • Exisiting house has now been relocated to the northern boundary.
  • Exterior fencing has now been installed and the site has been wrapped to promote further pre sales
  • Earthworks have commenced at the rear boundary of the site.
  • Stormwater and civil engineers are currently on site laying the footings for the foundation of the site.
  • Formwork to arrive on site in the new year.

Project Update as at 28th November 2016:

  • Site is currently being cleared and earthworks have commenced.
  • Relocation of services including power pole has now been completed.
  • Exisiting house is scheduled to be relocated on 6th December.
  • New pilings for existing house have been installed.
  • Marketing material and public pre sale campaign design will be finalised in December.
  • Slight modifications have been made to the roofline on the top floor above the 3 bedroom units in order to adhere to the adjacent charter listed properties. This does not effect the yield or size of the units in any way.

Project Update as at 24th October 2016

  • Construction loan settled on the 21st October
  • Civil and headworks to commence in 3 weeks.
  • Relocation of services and power pole to start 25th October.
  • Relocation of existing house will begin on the 2nd November.
  • Striping and small renovations on the existing building will start on the 5th November.
  • Marketing and sales campaign to begin around the 28th October.
  • Building approval to be concluded by the 13th November.


Project Update as at 16th September 2016

Land settled on 15th September.

Fixed build contract executed with Focus Management on 3rd September.

Civil and structure headworks to begin around the 28th September.

View DA Approved Plans

Da Approved Plans

Send us an email

Send us an email

We Find Houses
4/57 Township Drive
Burleigh Heads, Queensland 4220
Australia
Postal:
PO Box 105
West Burleigh, Queensland 4219
Australia
Phone: 1800 600 890
Business Hours: 9am – 5pm, Monday – Friday